Res 09-001
Res 09-001
CITY COMMISSION AGENDA 2
Meeting Date:
01/07/2009
Title:
Request for Approval of Award of Sanitary Sewer Rehabilitation Project Phase XI
Submitted For:
Mike Hogan
Submitted By:
Mike Hogan, Utilities
Department:
Utilities

ACTION REQUEST (Brief Summary)

Consider approval of Resolution No. 09-001 awarding the contract for the Sanitary Sewer Rehabilitaiton Project Phase XI.

BACKGROUND

This project includes approximately 20,000 linear feet of rehabilitation/replacement of sanitary sewer lines sized 8" diameter to 12" diameter.

ANALYSIS

Five bids were received.  The low bidder was Horseshoe Construction, Inc. with a total bid of $1,192,065.00.  Horseshoe Construction has performed numerous previous sanitary sewer rehabilitation projects for the City of Texas City and has always performed exceptionally well.

ALTERNATIVES CONSIDERED


Fiscal Impact

Funds Available Y/N:
Y
Amount Requested:
$1,192,065.00
Source of Funds:
Capital Budget
Account #:
510-702-55680-08014

Fiscal Impact:

Funds for this project are from capital project account 510-702-55680-08014 Sewer Line Improvements: Sewer Rehabilitation Phase XI.