ACTION REQUEST (Brief Summary)
Consider and take action on Resolution No. 18-021, approving and awarding a contract for bid # 2018-344 Force Main Pile Support Restoration Project. (Public Works)
BACKGROUND
On February 6, 2018, Notice was published and bid packets were made available from ARKK Engineers, through CivcastUSA. Bids were received and opened on February 22, 2018 at 2 pm.
The lowest responsible bidder meeting all requirements was RAC Industries, LLC, for the total amount of $114,094.40.
A bid tabulation and letter of recommendation from the project engineering firm, ARKK Engineers, is attached for your review.
The lowest responsible bidder meeting all requirements was RAC Industries, LLC, for the total amount of $114,094.40.
A bid tabulation and letter of recommendation from the project engineering firm, ARKK Engineers, is attached for your review.
ANALYSIS
It is the Recommendation of the Public Works Department that the City Commission award this project to RAC Industries, LLC for the total bid amount of $114,094.40 and authorize the Mayor to execute a contract on behalf of the City Commission. Public also requests that the Mayor be authorized to execute change orders not to exceed 25% of the amount bid, without bringing the matter before the Commission.