(6)(c)
CITY COMMISSION REGULAR MTG
Meeting Date:
04/04/2018
Title:
Extension of In-Pipe Contract
Submitted For:
Mike McKinley
Submitted By:
Mike McKinley, Public Works
Department:
Public Works

Information

ACTION REQUEST (Brief Summary)

Consider and take action on Resolution No. 18-029, approving a contract extension with In-Pipe Technology, LLC. (Public Works)

BACKGROUND

This process has effectively been able to comply with the Sanitary Sewer Overflow Initiative entered into by the City of Texas City with TCEQ to reduce sewer overflows.

In-Pipe Technology Company, LLC, Wheaton Illinois, is a sole source provider.

A copy of the Sole Source Justification, Contract Extension, and Performance Report, are attached for your review

ANALYSIS

It is the recommendation of the Public Works Department that the City Commission extend the Contract with In-Pipe Technology Company, LLC for a 24 month period at $14,200.00 per month. It is further requested that the Mayor be authorized to execute a contract extension on behalf of the City Commission.

Thank you.

ALTERNATIVES CONSIDERED


Fiscal Impact