ACTION REQUEST (Brief Summary)
Approval of GAMMA Constructions Guaranteed Maximum Price of $8,099,122.00, for the Police / Fire Department Training Facility.
BACKGROUND
GAMMA Construction has been hired by the City of Texas City as our Construction Manager At Risk for the fire training facility and they have finalized their GMP (Guaranteed Maximum Price). It is shown to be $8,099,122. The group will design and build at the same time the various facilities. The night of the approval there will be a powerpoint presentation that will go into more detail on the Fire Training Facility and the work by GAMMA Construction.
A copy of the agreement is attached for review.
A copy of the agreement is attached for review.
ANALYSIS
It is our recommendation that the City Commission accept and approve Gamma Construction's GMP of $8,099,122.00 and that the Mayor be authorized to enter into this agreement on behalf of the Commission.