- Meeting Date:
- 08/05/2020
- Title:
- Amend fiscal year 2019-20 budget
- Submitted For:
- Laura Boyd
- Submitted By:
- Laura Boyd, Finance
- Department:
- Finance
Information
ACTION REQUEST (Brief Summary)
BACKGROUND
A budget amendment is needed to appropriate additional funds for street improvement projects on 29th Street and Westbury Road and Tarpey Road.
From Public Works department:
TOTAL BID: $ 1,204,586.50 – AR Turnkee Construction
- 29th Street & Westbury Bid (Certificate Of Obligation) = $668,665.50
· Available Construction Budget is $801,294 after deducting engineering fee ($922,464.85-$121,170);
· Therefore remaining budget for 21st Street = $801,294 - $668,665.50 = $132,628.50
· Bid for 21st Street = $183,839
· Additional Budget Needed = $51,210.50 ($183,839-$132,628.50)
· Please note that Westbury and 21st street improvements was not part of the original project.
- Tarpey Road Construction Bid (acct # 411-301-55550): $ 352,082
· Available Construction Budget is $300,180 after deducting engineering fee ($350,000 -$49,820).
· Additional Construction Budget Needed = $51,902 ($352,082-$300,180)
· Increase due to the need for box culverts adjacent to homes.
Total Budget Needed for the Project - $51,210.50 + $51,902 = $103,112.50
ANALYSIS
General Fund (Fund 101) Department 301:
Street Improvements $103.500.00
Unassigned Fund Balance ($103,500.00)