(7)(k)
CITY COMMISSION REGULAR MTG
Meeting Date:
09/03/2025
Title:
Waterline Replacement Phase 22- Change Order
Submitted For:
Dj Hutchinson
Submitted By:
Dj Hutchinson, Public Works
Department:
Public Works

Information

ACTION REQUEST

Seeking City Commission Approval of Water Line Replacement Project Phase 22 - Change Order

BACKGROUND (Brief Summary)

The scope of work included in this Change Order included the installation of approximately 1060 Lf of 12" water line along Monticello. This work also included the installation of fire hydrants, valves, service connections, and all appurtenances required for the work. 
This 12" water line will replace the existing 811 water line, which is adjacent to the current College of the Mainland building construction. 

RECOMMENDATION

It is the recommendation of the Public Works Department to consider and approve this item.

Fiscal Impact

Funds Available Y/N:
Yes
Amount Requested:
159,875.00
Source of Funds:
FY 24/25 Budget
Account #:
501705-55690

Fiscal Impact:

Bringing the total contracted amount to 1,532,827.00. Previously approved in Resolution No. 2025-050.

Attachments