Res 08-006
Res 08-006
CITY COMMISSION AGENDA
- Meeting Date:
- 01/16/2008
- Title:
- Galveston County MUD No. 54 Water Well and Plant
- Submitted By:
- Rita Williams, Purchasing
- Department:
- Purchasing
ACTION REQUEST (Brief Summary)
Approve to recommend that Galveston County M.U.D. #54 award construction contract for the water well/plant project to the apparent low bidder, R & B Group, for their total bid amount of $2,335,000.00.
BACKGROUND
This is the first phase construction of the major water plant/pump station facility for the west side of Texas City. The water well is needed for an emergency backup water supply and will be necessary for all the new development on the west side of Texas City.
ANALYSIS
Bid documents were received by three (3) contractors on Thursday, January 10, 2008. A bid tabulation is attached for your review. This project is being funded from Capital Recovery Fees; of which a large portion is provided by Galveston M.U.D. #54.
ALTERNATIVES CONSIDERED
Fiscal Impact
- Funds Available Y/N:
- NO
- Amount Requested:
- $2,335,000
- Source of Funds:
- Galveston Co. MUD #54
- Account #:
- None
Fiscal Impact:
City is reccomending to Galveston County MUD #54 to accept this bid. City does not have the funding for the project, nor is it responsible for the funding. This is a "pass-through" project, the City will receive the invoices for the project, invoices will not be paid or entered into the City's budgeting system, they will be forwarded directly to Galveston County MUD #54 for processing and payment.