(7)(k)
CITY COMMISSION REGULAR MTG
- Meeting Date:
- 09/03/2025
- Title:
- Waterline Replacement Phase 22- Change Order
- Submitted For:
- Dj Hutchinson
- Submitted By:
- Dj Hutchinson, Public Works
- Department:
- Public Works
Information
ACTION REQUEST
Seeking City Commission Approval of Water Line Replacement Project Phase 22 - Change Order
BACKGROUND (Brief Summary)
The scope of work included in this Change Order included the installation of approximately 1060 Lf of 12" water line along Monticello. This work also included the installation of fire hydrants, valves, service connections, and all appurtenances required for the work.
This 12" water line will replace the existing 811 water line, which is adjacent to the current College of the Mainland building construction.
This 12" water line will replace the existing 811 water line, which is adjacent to the current College of the Mainland building construction.
RECOMMENDATION
It is the recommendation of the Public Works Department to consider and approve this item.
Fiscal Impact
- Funds Available Y/N:
- Yes
- Amount Requested:
- 159,875.00
- Source of Funds:
- FY 24/25 Budget
- Account #:
- 501705-55690
Fiscal Impact:
Bringing the total contracted amount to 1,532,827.00. Previously approved in Resolution No. 2025-050.