W.O. 11-01 Water Main Replacement Projects, Contract Award
PRESENTED BY:
David Mumford
Department:
Public Works
Presentation:

PROBLEM/ISSUE STATEMENT

The City Council is asked to consider authorizing construction contracts for Schedules 1 and 2 of W.O. 11-01, Water Main Replacement Projects.  Schedule 1 work will take place in 4th Avenue North between North 18th and North 28th Street and will install approximately 2,130 feet of 24-inch and 1,580 feet of 16-inch water main.  Schedule 2 replacement work will occur in North 33rd, 34th and 35th Street between Montana Avenue and Division Street.  Schedule 2 bid alternates include work in 1st and 2nd Avenue North between North 33rd and Division Street.  Schedule 2 work will install approximately 6,100 feet of 12-inch water main.

ALTERNATIVES ANALYZED

The Council may:

• Award construction contracts to Western Municipal Construction for Schedule 1 and COP Construction for Schedule 2.
• Reject all bids and do not award construction contracts on Schedules 1 and 2.

FINANCIAL IMPACT

Bids were opened on May 10, 2011 for W.O. 11-01 with the results listed below:

Schedule 1 - 4th Avenue North Water Main Replacement

Open Cut
Engineer's Estimate:  $2,324,207.00
Western Municipal Construction:  $2,294,378.00
COP Construction LLC:  $2,338,652.00
Ahanu Construction Inc.:  $2,654,097.50

Trenchless Alternate
Engineer's Estimate: $2,096,776.00
Western Municipal Construction:  No Bid
COP Construction LLC:  No Bid
Ahanu Construction Inc.:  No Bid

Schedule 2 - Division Street/Montana Avenue Triangle Area Water Main Replacement

SCH 2A--North 33rd, 34th, and 35th Street Replacement
Engineer's Estimate:  $1,476,261.00
Western Municipal Construction:  $1,437,800.00
COP Construction LLC:  $1,434,609.00
Ahanu Construction Inc.:  $1,878,226.00

SCH 2B--1st Avenue North Replacement Alternates
• Open Cut
Engineer's Estimate:  $300,205.00
Western Municipal Construction:  $247,841.50
COP Construction LLC:  $224,186.00
Ahanu Construction Inc.:  $315,777.50
• Trenchless PVC
Engineer's Estimate:  $239,320.00
Western Municipal Construction:  No Bid
COP Construction LLC:  No Bid
Ahanu Construction Inc.:  No Bid
• Trenchless Ductile Iron
Engineer's Estimate:  $254,386.00
Western Municipal Construction: No Bid
COP Construction LLC: No Bid
Ahanu Construction Inc.: No Bid

SCH 2C--2nd Avenue North Replacement Alternate
• Open Cut
Engineer's Estimate:  $231,785.00
Western Municipal Construction:  $224,736.00
COP Construction LLC:  $184,137.00
Ahanu Construction Inc.:  $255,920.00


Low Bid--Schedule 1 to Western Municipal Construction:  $2,294,378.00

Low Bid--Schedules 2A ($1,434,609.00), 2B ($224,186.00) and 2C ($184,137.00) to COP Construction LLC:  $1,842,932.00

This project will utilize Water Funds budgeted in FY 11.

RECOMMENDATION

Staff recommends that Council approve a construction contract for Schedule 1 of W.O. 11-01 for Western Municipal Construction in the amount of $2,294,378.00. Staff recommends that Council approve a construction contract for Schedule 2A, 2B and 2C for COP Construction LLC in the amount of $1,842,932.00.