Item 1.A.1.
|
| City Council Regular | |
| Date: | 07/28/2025 |
| Title: | Bid Award Big Ditch Trail Extension - Knife River |
| Presented by: | Brad Wright |
| Department: | Parks/Rec/Public Lands |
| Presentation: | No |
| Legal Review: | Not Applicable |
| Project Number: | N/A |
RECOMMENDATION
PRPL seeks Council consent to award Knife River the contract for the Big Ditch Trail Extension. The contract will be in the amount of $105,575.00. The scope of work will include 9,650 SF of new concrete sidewalk, fine grading, and seeding/restoration of disturbed areas.
BACKGROUND (Consistency with Adopted Plans and Policies, if applicable)
Big Ditch Trail Ext is a joint-funded project through Montana Fish Wildlife and Parks (FWP) and Billings Trail Net. The new concrete sidewalk will be a multi-use sidewalk starting from the southwest corner of Rimrock West Park and moving west through park-owned property. The sidewalk will terminate with a handicap ramp on Stone Creek Rd in the River Rock Estates Subdivision. Funding for the project totals $138,023.00. FWP $84,182.00 Billings Trail Net $53,841.00. Of that, $138,023.00, $24,500.00 was used for consulting, survey, design and a bid package. There is a balance of $113,523.00 to complete the project. Once PRPL receives Council consent, a notice to proceed will be given; PRPL expects to complete the project by 12/31/2025.
STAKEHOLDERS
City of Billings
PRPL
River Rock Estates Subdivision
Park and trail users
Billings Trail Net
Knife River
PRPL
River Rock Estates Subdivision
Park and trail users
Billings Trail Net
Knife River
ALTERNATIVES
City Council may:
- Approve; or,
- Not Approve
FISCAL EFFECTS
Although construction costs are covered, PRPL does expect to see a minimal cost increase over time due to the added time for maintenance the new trail will cause. (Example - Snow removal.) Maintenance costs are minimized due to the trail being done in concrete. PRPL does not expect to hire any FTEs.
There were 7 bidding companies:
There were 7 bidding companies:
| Contractor | Base Bid |
| K2 Ventures | $124,987 |
| 7F Services | $114,368 |
| K2 Civil | $183,580 |
| EMX | $244,720 |
| Knife River | $105,575 Winning Bid |
| Askin Construction | $151,260 |
| Weave Construction | $140,669 |