TITLE
W.O. 11-05, Chapple Area Water Main Improvement Projects
PRESENTED BY:
David Mumford
Department:
Public Works
Presentation:

PROBLEM/ISSUE STATEMENT

The City Council is asked to consider authorizing a construction contract for W.O. 11-05, Chapple Area Water Main Improvement Projects. Over 6,000 lineal feet of water main and related improvements will be constructed and replaced by these projects. Work will generally take place in Arnold Palmer Drive, Mickey Wright Lane, 40th Street West, Powderhorn Drive, Snowcrest Drive, 37th Street West, and Palisades Park Drive between Rimpoint Drive and High Park Drive.

ALTERNATIVES ANALYZED

The Council may:

• Award a construction contract to the low bidder, Ahanu Construction.
• Reject all bids and not award a construction contract to the low bidder, Ahanu Construction.

FINANCIAL IMPACT

Bids were opened on June 14, 2011 for W.O. 11-05 with the results listed below:


Bidder Total Bid
COP Construction, LLC         $1,019,752.00
Western Municipal Construction, Inc.          $916,000.00
Ahanu Construction          $830,065.00
Johnston Excavating, Inc.         $1,083,203.00
Engineer's Estimate         $1,309,323.50


Project funding will be through City water funds.

RECOMMENDATION

Staff recommends that Council approve a construction contract for W.O. 11-05 for Ahanu Construction in the amount of $830,065.00.