Consent 1.C.
Regular City Council Meeting
- Meeting Date:
- 06/27/2011
- TITLE
- WO 09-14 Wicks and Saint Andrews Signal Change Order #2 Final
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
PROBLEM/ISSUE STATEMENT
WO 09-14, Wicks and Saint Andrews Signal, was awarded on September 27, 2010. This project constructed a traffic signal at the intersection of Wicks Lane and Saint Andrews Drive and is close to being substantially complete. On December 8, 2010, Change order #1 was approved to add an Accessibility System to the traffic signal in the amount of $8,500. Change order #2 (final) will add a luminaire to the northeast corner of the intersection and reconciles final quantities with bid quantities in the amount of $5,491.53. Change order #2, combined with change order #1, is more than 10% of the original contract amount, therefore requiring approval from the City Council.
ALTERNATIVES ANALYZED
The Council may:
- Approve change order #2 for Work Order 09-14 to reconcile the project and add a luminaire; or
- Do not approve the change order and eliminate the luminaire ($3,300) from the project. The reconciling portion of the change order would need to be approved to close out the project ($2,191.53).
FINANCIAL IMPACT
Funding for WO 09-14 Wicks and Saint Andrews Signal and the change orders is being provided from Arterial Funds. The final contract amount is $121,909.53.
RECOMMENDATION
Staff recommends that Council approve the change order #2 final for WO 09-14 Wicks and Saint Andrews Signal in amount of $5,491.53.