TITLE
W.O. 12-04 Accessibility Ramp Project Bid Award
PRESENTED BY:
David Mumford
Department:
Public Works
Presentation:

Information

PROBLEM/ISSUE STATEMENT

Bids were received on March 27, 2012, for W.O. 12-04 Accessibility Ramp Project. The project will replace existing and construct new accessibility ramps along portions of Virginia Lane, Lewis Avenue, and 36th Street West.  Per the agreement between the U.S. Department of Justice and the City Of Billings, the City is required to construct accessibility ramps on all streets that have been reconstructed or overlaid since 1992.

ALTERNATIVES ANALYZED

The Council may:

• Award the construction contract for W.O. 12-04 Accessibility Ramp Project to J & J Concrete, Inc. in the amount of $249,345.00; or
• Reject all bids and do not award a construction contract for W.O. 12-04.  Rejection of bids will delay construction of these improvements until next year. 

FINANCIAL IMPACT

The City received four (4) bids for this project.  The bids were as follows: 

Contractor Total Construction Bid
J & J Concrete $249,345
CMG Construction $285,759
Riverside Sand & Gravel $286,237
H.L. Ostermiller $299,963
   












The funding for the project was budgeted in FY12 and the source is gas tax.  A summary of the funding is as follows:

Project Budget $250,000
Previously Encumbered $0
This Contract $249,345
Budget Remaining $655

 

 

RECOMMENDATION

Staff recommends that Council award the contract for Work Order 12-04 Accessibility Ramp Project to J &J Concrete Inc. in the amount of $249,345.