Consent 1.A.3.
Regular City Council Meeting
- Meeting Date:
- 09/10/2012
- TITLE
- Award of the Pond C Outfall Improvements for Billings Logan International Airport
- PRESENTED BY:
- Tom Binford
- Department:
- Airport
Presentation:
Information
PROBLEM/ISSUE STATEMENT
Included in the Airport's Capital Improvement Program is the Pond C Outfall Improvement Project. As a result of the extreme rainfall events of 2010 and 2011, the Airport has undertaken measures to improve the Airport's storm water detention ponds. This is the third project the Airport has undertaken to improve storm detention ponds A, B, and C . The first two projects increased the capacity of the ponds to hold a 100-year 24-hour rain event and upgraded the dikes around the ponds to withstand the potential impacts of higher pond levels. The heavy rainfall associated with the Fathers Day storm in 2010 and the record setting May 24, 2011 storm both produced more rain water than the detention ponds were designed to hold, and for the first time since the ponds were constructed in 1976, excess water flowed out of Pond C and into the natural drainage and down into the Moon Valley subdivision. Working with the consent of the current property owner in Moon Valley, where the majority of the water flowed, this project will construct a swale from the outfall of Pond C to the edge of the rims, a plunge pool/energy dissipater at the bottom to the rims to collect the water and reduce its velocity, and a spillway from the plunge pool to the street with three additional energy dissipating baffles to further reduce the water's velocity. Again, this is an emergency relief system that will hopefully never need to be used, but will be in place should the Airport ever incur another 100+ year storm. This project was advertised in the Billing Times for three weeks, and was on the City's Website. On August 28, 2012, the following bids were received for this project:
| Contractor | Bid |
| The Good Earth Works Company, Inc. | $70,100 |
| Donnes, Inc. | $85,050 |
ALTERNATIVES ANALYZED
The City Council may:
- Approve the low bid and award the contract for the Pond C Outfall Improvement Project; or
- Reject all bids and delay the project.
FINANCIAL IMPACT
The total cost of this project is $70,100. Funds are available in the Airport's Passenger Facility Charge (PFC) capital account.
RECOMMENDATION
Staff recommends that the City Council approve and award the Pond C Outfall Improvements to the low bidder, The Good Earth Works Company, Inc., for the amount of $70,100.
APPROVED BY CITY ADMINISTRATOR