- South Park Gazebo Change Order #3
- PRESENTED BY:
- Mike Whitaker
- Department:
- Parks/Rec/Public Lands
Presentation:
Information
PROBLEM/ISSUE STATEMENT
On July 23, 2012, Council approved a contract with Fisher Construction, Inc. to construct the new gazebo at South Park. As the project has proceeded there have been some unforeseen issues surface requiring additional work and materials. Change Order #3 addresses these issues. Cost of this change order is $5,979.00 and will be covered by the project contingency.
ALTERNATIVES ANALYZED
Council may:
- Approve Change Order #3.
- Not approve Change Order #3 and provide direction to staff.
FINANCIAL IMPACT
The total cost for Change Order #3 is $5,979.00 and will be covered by the project funds. There will be no financial impact to the City.
RECOMMENDATION
Staff recommends that the City Council approve Change Order #3 in the amount of $5,979.00 to fund this additional work to the South Park Gazebo project.