Regular 2.
Regular City Council Meeting
- Meeting Date:
- 04/08/2013
- TITLE
- W.O. 13-02 Miscellaneous/Developer Related - Public Hearing and Resolution Ordering Improvements
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
Information
PROBLEM/ISSUE STATEMENT
On March 11, 2013, Council passed a Resolution of Intent for the Miscellaneous/Developer Related improvements project and established a Public Hearing date of April 8, 2013. After conducting the Public Hearing, Council must pass a resolution ordering construction of improvements in order for the project to proceed. The project consists of curb, gutter, sidewalk, and storm drain improvements at various locations around the city. It consists of unfulfilled building permit obligations and the continuation of annual improvements that deal with tripping hazards, drainage problems, property owner requests, complaints, and other miscellaneous concrete work brought to the attention of the City Engineer's Office.
ALTERNATIVES ANALYZED
The Council may:
• Pass a resolution ordering construction of the improvements; or
• Do not pass a resolution ordering construction of the improvements. If the Council does not pass the Resolution, the property owners cannot be assessed and the work will not occur because there is no other source of funding.
• Pass a resolution ordering construction of the improvements; or
• Do not pass a resolution ordering construction of the improvements. If the Council does not pass the Resolution, the property owners cannot be assessed and the work will not occur because there is no other source of funding.
FINANCIAL IMPACT
The proposed project is funded through multiple sources, including direct property assessments, for a total budgeted amount of $732,500.
The Capital Improvement Plan shows this project and adequate funding is appropriated in the Fiscal Year 2013 Budget.
| Estimated Assessed Costs | $425,000 |
| Storm Drain Funds | $52,500 |
| Gas Tax Funds | $250,000 |
| Water and Sewer Funds | $5,000 |
The Capital Improvement Plan shows this project and adequate funding is appropriated in the Fiscal Year 2013 Budget.
RECOMMENDATION
Staff recommends that Council conduct a public hearing and approve a resolution ordering construction of the improvements identified in Work Order 13-02, Miscellaneous/Developer Related.