TITLE
W.O. 09-12 Inner Belt Loop Phase I Bid Award
PRESENTED BY:
David Mumford
Department:
Public Works
Presentation:

Information

PROBLEM/ISSUE STATEMENT

W.O. 09-12, Inner Belt Loop Phase I, will construct an arterial road between Wicks Lane and Alkali Creek Road. Improvements include constructing the road, multi-use path, culverts for Alkali Creek, storm drain facilities, and signing and striping. The project was advertised on August 15, 22, 29, and September 5, 2013, in the Billings Times and on the City's website. Bids were opened on September 10th and three bids were received. Riverside Contracting, Inc. submitted the lowest responsible bid.

ALTERNATIVES ANALYZED

The Council may:
  • Award W.O. 09-12 to Riverside Contracting, Inc. in the amount of $2,169,126.00; or
  • Not award the contract to Riverside Contracting, Inc. and reject all bids. If this project is not constructed, an additional route out of the West Heights will not be built. 

FINANCIAL IMPACT

The following bids were received and evaluated:

CONTRACTOR CONTRACT
Riverside Contracting, Inc. $2,169,126.00
CMG Construction, Inc $2,805,683.00
Knife River - Billings $2,991,948.70

The funding for the project was budgeted in FY14 and the source is Arterial Fee funds.

Project Budget $3,000,000.00
This Contract $2,169,126.00
Project Budget Remaining $   830,874.00

RECOMMENDATION

Staff recommends City Council award a contract for W.O. 09-12 Inner Belt Loop Phase 1 to Riverside Contracting, Inc. in the amount of $2,169,126.00.