W.O. 10-08 Water Treatment Plant Clearwell Baffle Project Contract Amendment No. 4
PRESENTED BY:
David Mumford
Department:
Public Works
Presentation:

Information

PROBLEM/ISSUE STATEMENT

Staff is requesting that the City Council consider authorizing and executing a Contract Amendment for Professional Services with Morrison-Maierle for construction administration services for W.O. 10-08 Water Treatment Plant Clearwell Baffle Project.  The original construction contract duration for coating the tank and installing the baffles for Clearwell No. 1 was 75 calendar days. Due to the replacement of the roof, an additional 105 calendar days were added to the contract.  Morrison-Maierle's contract for the design and construction administration services does not account for the additional inspection time required for the increased duration of the construction contract. 

ALTERNATIVES ANALYZED

Council may:
  • Approve Contract Amendment No. 4 with Morrison-Maierle for additional construction administration services in the amount of $11,619.00; or
  • Do not approve Contract Amendment No. 4 with Morrison-Maierle. If the Contract Amendment is not approved Morrison-Maierle will not get paid for additional construction administration performed due to unforeseen changes and delays which increased the duration of the construction process. 

FINANCIAL IMPACT

Funds for Contract Amendment No. 4 are available from FY14 Water Revenues.  If approved, the Professional Services Contract with Morrison-Maierle will total $176,544.00