TITLE
WO 10-03 2010 Street Maintenance City Chip Seal
PRESENTED BY:
David Mumford
Department:
Public Works
Presentation:

PROBLEM/ISSUE STATEMENT

Bids were received and evaluated for the 2010 Street Maintenance Program, City Chip Seal on January 26, 2010. This project will chip seal various streets throughout the city. Approximately 13 miles of residential and commercial streets will be chip sealed.

ALTERNATIVES ANALYZED

The Council may:
• Award Work Order 10-03, 2010 Street Maintenance Program, City Chip Seal, to Knife River - Billings in the amount of $420,810.22; or
• Reject all bids and not award Work 10-03, 2010 Street Maintenance Program, City Chip Seal.

FINANCIAL IMPACT

Funding for the 2010 Street Maintenance Program, City Chip Seal, will be provided from FY10 Gas Tax Funds totaling $466,000.  We received five bids for this project as follows:

WO 10-03 City Chip Seal Bids
Contractor Bid Amount
Engineer's Estimate $475,428.70
Knife River-Billings $420,810.22
Riverside Sand & Gravel $498,498.78
Ostermiller Construction $503,591.31
Hardrives Construction $531,915.46
Pavement Maintenance Solutions $564,194.84

RECOMMENDATION

Staff recommends that Council approve the construction contract for the Street Chip Seal Maintenance Project with Knife River - Billings in the amount of $420,810.22.