TITLE
W.O. 15-15 Shawnee Drive Improvements - Bid Award
PRESENTED BY:
David Mumford
Department:
Public Works
Presentation:

PROBLEM/ISSUE STATEMENT

W.O. 15-15 - Shawnee Drive Improvements will construct approximately 250 feet of street improvements including curb, gutter, and asphalt on Shawnee Drive east of Main Street.  Shawnee Drive is currently a gravel street without improvements.

The project was advertised on July 21st, 28th, and August 4th in the Billings Times and on the City's Website.  Bids were opened on August 11, 2015.  The City received six bids and Winkler Excavating, Inc. submitted the lowest responsible bid. 

ALTERNATIVES ANALYZED

City Council may:
  • Approve W.O. 15-15 Shawnee Drive improvements to Winkler Excavating, Inc. in the amount of $88,126.00, or;
  • Do not award W.O. 15-15.  If not awarded, Shawnee Drive will remain a gravel street.

FINANCIAL IMPACT

The following bids were received and evaluated:
 
Contractor Total Bid
Winkler Excavating, Inc. $88,126.00
Knife River $96,373.50
H.L. Ostermiller $98,297.20
Wharton Asphalt $104,495.35
CMG $122,970.00
Asphalt Plus $97,000

The project was funded in FY 15 with gas tax and a budget amendment request will be submitted to Council to transfer the funds to FY16.

RECOMMENDATION

Staff recommends Council award W.O. 15-15; Shawnee Drive Improvements, to Winkler Excavating, Inc. in the amount of $88,126.00.

APPROVED BY CITY ADMINISTRATOR