Consent 1.D.
Regular City Council Meeting
- Meeting Date:
- 04/12/2010
- TITLE
- W.O. 09-26 Contract for Professional Services for WWTP Clarifier Infrastructure Replacement -
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
PROBLEM/ISSUE STATEMENT
Mayor and Council are asked to consider authorizing the Mayor to execute a Contract for Professional Services with Morrison-Maierle, Inc. to provide engineering design and construction services for W.O. 09-26, WWTP Clarifier Infrastructure Replacement. The primary and secondary clarifiers at the Waste Water Treatment Plant need to have general maintenance performed and some equipment replaced. The purpose of this project is to sand blast and re-coat all metal inside the clarifiers including the catwalks, turntables, and drives; replace the grease traps in the primary clarifiers; and patch concrete in the clarifiers. Morrison-Maierle, Inc. was selected for this work based on City staff review of project proposals submitted by prequalified firms.
ALTERNATIVES ANALYZED
The Council may:
- Approve the Contract for Professional Services with Morrison-Maierle, Inc.; or
- Do not approve the Contract for Professional Services with Morrison-Maierle, Inc.
FINANCIAL IMPACT
Funding for the design and construction of this project is included in the FY 2010 budget in the amount of $327,000.
RECOMMENDATION
Staff recommends that Council authorize the Mayor to sign a contract for professional design and construction management services with Morrison-Maierle, Inc. for W.O. 09-26, WWTP Clarifier Infrastructure Replacement in the amount not to exceed $53,925.00.