Consent 1.B.3.
Regular City Council Meeting
- Meeting Date:
- 05/10/2010
- TITLE
- W.O. 08-21 Lake Elmo Drive - Main St to Wicks Ln Bid Award
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
PROBLEM/ISSUE STATEMENT
Bids were received for W.O. 08-21 Lake Elmo Drive on April 27, 2010. The project will include street reconstruction with turn lanes, pavement overlay, curb, gutter, sidewalk, drive approaches, storm drain improvements, and an asphalt multi-use trail along Lake Elmo Drive from Main Street to Wicks Lane.
ALTERNATIVES ANALYZED
The Council may:
• Award the contract W.O. 08-21 to Riverside Sand & Gravel in the amount of $1,689,497.00; or
• Reject all bids and do not award contract for W.O. 08-21
• Award the contract W.O. 08-21 to Riverside Sand & Gravel in the amount of $1,689,497.00; or
• Reject all bids and do not award contract for W.O. 08-21
FINANCIAL IMPACT
We received five (5) bids for this project as follows:
Engineer's Estimate $2,252,130.00
The following is a breakdown of the project funding sources available:
Estimated Assessed Costs $472,000
CTEP $552,591
Storm Drain Funds $510,000
Gas Tax Funds $1,655,000
Total Funding Available $3,189,591.00
The following is a breakdown of the costs of the $3,189,591.00 allocated for this project:
Design $233,113.00 (PE contract)
Staking $126,590.00
Construction $1,689,497.00
Remaining Funds $1,140,391.00
Remaining funds will be used for change orders, materials testing, inspection, and other administrative costs.
Engineer's Estimate $2,252,130.00
| Contractor | Total Construction Bid |
| Riverside Sand & Gravel | $1,689,497.00 |
| H.L. Ostermiller | $1,801,380.30 |
| Knife River | $1,932,237.50 |
| CMG Construction, Inc. | $2,025,653.00 |
| JEM | $2,299,609.10 |
The following is a breakdown of the project funding sources available:
Estimated Assessed Costs $472,000
CTEP $552,591
Storm Drain Funds $510,000
Gas Tax Funds $1,655,000
Total Funding Available $3,189,591.00
The following is a breakdown of the costs of the $3,189,591.00 allocated for this project:
Design $233,113.00 (PE contract)
Staking $126,590.00
Construction $1,689,497.00
Remaining Funds $1,140,391.00
Remaining funds will be used for change orders, materials testing, inspection, and other administrative costs.
RECOMMENDATION
Staff recommends that Council award the bid for Work Order 08-21 Lake Elmo Drive, Main Street to Wicks Lane, to Riverside Sand & Gravel in the amount of $1,689,497.00.
APPROVED BY CITY ADMINISTRATOR