Skip to main content

AgendaQuick™

View Agenda Item

Consent   1.A.2.
Regular City Council Meeting
Meeting Date:
05/08/2017
TITLE
Bid Award: W.O. 17-04; 2015 ADA Ramp Replacement Project
PRESENTED BY:
David Mumford
Department:
Public Works
Presentation:

PROBLEM/ISSUE STATEMENT

W.O. 17-04, 2017 ADA Ramp Replacement Project, is a project consisting of Americans with Disabilities Act (ADA) accessible ramp construction on the street corners where the City will soon be completing pavement overlays and chip seals and on other corners at various locations throughout Billings.

The annual ramp construction project is in accordance with the City’s agreement with the Department of Justice to install/upgrade ramps along streets constructed or reconstructed after 1992 and in specific areas identified by need. A portion of the ramps will be constructed on Division Street ahead of the MDT pavement overlay project.  The other miscellaneous ramp locations were selected based upon neighborhood requests.

The project was advertised on April 13th and April 20th in the Billings Times and on the City's Website. Bids were opened on April 25, 2017 and seven bids were received.  LGI Construction submitted the lowest responsible bid.

ALTERNATIVES ANALYZED

The Council may:
  • Award Work Order 17-04, 2017 ADA Ramp Replacement Project to LGI Construction in the amount of $249,190; or
  • Do not award Work Order 17-04.  If not awarded, the City would need to re-bid or cancel the project and construct the ramps in a subsequent year.

FINANCIAL IMPACT

The following bids were received and evaluated:
 
Contractor  Total Bid
LGI Construction $249,190.00
J&J Concrete, Inc. $252,250.00
EHC, LLC $269,425.50
CMG Construction $287,448.50
Askin Construction $298,646.00
AV Construction $366,387.50
Knife River $401,250.00

The funding for this project is included in the approved budget for fiscal year 2017.  Gas Tax funds will be used for this project. 
 
Budget $300,000
Previously Encumbered $0
This contract $249,190
Remaining Budget $50,810

RECOMMENDATION

Staff recommends that Council award W.O. 17-04, 2017 ADA Ramp Replacement Project to LGI Construction in the amount of $249,190.

APPROVED BY CITY ADMINISTRATOR