TITLE
Bid Award: W.O. 18-10 Poet Streets
PRESENTED BY:
David Mumford
Department:
Public Works
Presentation:
No

PROBLEM/ISSUE STATEMENT

Staff opened bids on February 13, 2018, for the Poet Streets project. There were four bids and Askin Construction LLC submitted the lowest responsible bid.  The project will overlay the roads in the Poet Streets neighborhood and add curbing. These streets are currently not on the Street Preventative Maintenance Program and the project will allow them to be incorporated into the program in the future. The project was advertised in The Yellowstone County News January 26th, February 2nd, and February 9th and on the City's website.

ALTERNATIVES ANALYZED

City Council may:
  • Award W.O. 18-10 Poet Streets to Askin Construction, LLC, in the amount of $793,896.94, or;
  • Not award the contract to Askin Construction, LLC, and reject all bids.  If the contract is not awarded, the neighborhood streets will remain non-maintainable by the standards of the Street Preventative Maintenance Program and will continue to degrade.

FINANCIAL IMPACT

The following bids were received and evaluated:
CONTRACTOR BASE BID
Askin Construction, LLC $793,896.94
CMG Construcion, LLC $798,744.00
Knife River - Billings $979,748.25
Wharton Asphalt, LLC $1,012,927.35
 

The funding for the project was budgeted in FY18 and the source is the gas tax and SID bonds.
Project Budget $1,207,900.00
Previously Encumbered $24,198.00
This Contract $793,896.94
Remaining Budget $389,805.06

RECOMMENDATION

Staff recommends the City Council award a contract for W.O. 18-10 Poet Streets to Askin Construction, LLC, in the amount of $793,896.94.