Consent 1.A.3.
Regular City Council Meeting
- Meeting Date:
- 01/14/2019
- TITLE
- W.O. 18-24; WRF Administration Building Improvements
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
No
PROBLEM/ISSUE STATEMENT
W.O. 18-24, WRF Administration Building Improvements is a project to expand the existing Administration Building at the Water Reclamation Facility. A single bid from Sletten Construction in a total amount of $3,498,100.00 was received on December 18. This amount is significantly greater than the budgeted amount and staff is recommending that Council not approve the contract. The expansion plans will be modified and rebid at a later time.
ALTERNATIVES ANALYZED
City Council may:
- Approve award of the construction contractor to Sletten Construction, or;
- Reject the bid for the project.
FINANCIAL IMPACT
A single bid was received on December 18, 2018 for W.O. 18-24; WRF Administration Building Improvements project. The bid was from Sletten Construction Company in the amount of $3,498,100. The available budget is $2.1 million.
RECOMMENDATION
Staff recommends that City Council not award a construction contract for W.O. 18-24, WRF Administration Building Improvements.