Consent   1.A.3.
Regular City Council Meeting
Meeting Date:
06/10/2019
TITLE
Bid Award - W.O. 19-44: Shiloh Roundabouts Landscaping
PRESENTED BY:
David Mumford
Department:
Public Works
Presentation:
No

PROBLEM/ISSUE STATEMENT

W.O. 19-44: Shiloh Roundabouts Landscaping Project includes landscape modifications of six existing roundabouts in Shiloh Road. The roundabouts included in this scope are: Broadwater, Central, Monad, King, Knife River, and Hesper. The general scope for each roundabout includes: demolition, grading, layout, retaining wall construction, boulder placement, tree & shrub planting, mulch bed construction, weed fabric, and irrigation improvements.  The goal of the project is to reduce the amount of time required for maintenance of the roundabouts. The project was advertised May 17th and 24th, 2019, in the Yellowstone County News. Bids were opened on May 28th. There were two bids received and Good Earth Works submitted the lowest responsible bid.

ALTERNATIVES ANALYZED

City Council may:
  • Award W.O. 19-44: Shiloh Roundabouts Landscaping Project to Good Earth Works, in the amount of $1,196,915.00; or
  • Do not award a contract and reject all bids. If the contract is not awarded the landscape modifications of the six Shiloh Roundabouts cannot be completed.

FINANCIAL IMPACT

The following bids were received and evaluated:
 
Contractor Total Contract Bid Price for All Bid Schedules 1-6
Good Earth Works  $1,196,915.00
Huppert Brothers $1,265,900.00

The funding source is street maintenance district funds budgeted in FY19.

RECOMMENDATION

Staff recommends the City Council award a contract for W.O. 19-44: Shiloh Roundabouts Landscaping Project to Good Earth Works in the amount of $1,196,915.00.