Consent 1.A.3.
Regular City Council Meeting
- Meeting Date:
- 09/23/2019
- TITLE
- Bid Award - W.O. 19-35: Zone 1 WTP Waterline Improvements
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
No
PROBLEM/ISSUE STATEMENT
W.O. 19-35 Zone 1 WTP Waterline Improvements is a project to:
- install piping to connect zone 2 to zone 1;
- split zone 1 into two zones: zone 1 north and zone 1 south; and
- replace old waterlines within the water plant complex.
ALTERNATIVES ANALYZED
The Council may:
- Award W.O. 19-35: Zone 1 WTP Waterline Improvements, to Western Municipal Construction, in the amount of $1,309,900.00; or
- Do not award a contract and reject all bids. If the contract is not awarded, the work can not be done which will result in having less reliability than is desired or recommended within the water system.
FINANCIAL IMPACT
The following bids were received and evaluated:
The funding source is water funds budgeted in FY 20.
| Contractor | Total All Schedules |
| COP Construction | $1,449,100 |
| Western Municipal Construction | $1,309,900 |
The funding source is water funds budgeted in FY 20.
RECOMMENDATION
Staff recommends the City Council award a contract for W.O. 19-35 Zone 1 WTP Waterline Improvements to Western Municipal Construction in the amount of $1,309,900.