Consent 1.B.1.
Regular City Council Meeting
- Meeting Date:
- 02/28/2011
- TITLE
- WO 11-03 2010 Street Maintenance Program, City Overlay
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
PROBLEM/ISSUE STATEMENT
Bids were opened February 15, 2011, for the 2011 Street Maintenance Program, City Overlay. This project will overlay 24th Street West from Central to Grand, Grand Avenue from 24th Street West to the BBWA Canal and 1st Avenue North from 18th to 31st.
ALTERNATIVES ANALYZED
The Council may:
• Award Work Order 11-03, 2011 Street Maintenance Program, City Overlay, to Riverside Contracting in the amount of $881,913.17; or
• Reject all bids and not award Work 11-03, 2011 Street Maintenance Program, City Overlay.
• Award Work Order 11-03, 2011 Street Maintenance Program, City Overlay, to Riverside Contracting in the amount of $881,913.17; or
• Reject all bids and not award Work 11-03, 2011 Street Maintenance Program, City Overlay.
FINANCIAL IMPACT
Funding for the 2011 Street Maintenance Program, City Overlay, will be provided from FY11 Gas Tax, the Arterial allocation for PAVER and $300,000 from the MDT annual maintenance of State Routes agreement. The City received 4 bids for this project as follows:
| Contractor | Bid Amount |
| Engineer's Estimate | $819,889 |
| Riverside | $881,913.17 |
| Ostermiller | $887,689.87 |
| Hardrives | $897,967.95 |
| Knife River | $981,300.95 |
RECOMMENDATION
Staff recommends that Council approve the construction contract for the Street Maintenance Program, City Overlay project with Riverside Contracting in the amount of $881,913.17.
APPROVED BY CITY ADMINISTRATOR
Attachments
No file(s) attached.