Item 1.E.
 
City Council Regular
Date: 09/25/2023
Title: New City Hall Professional Services Amendment No. 3
Presented by: Jessica Fust, Building Official
Department: City Hall Administration
Presentation: No
Legal Review: Yes
Project Number: N/A

RECOMMENDATION

Staff recommends Council approve an amendment to the New City Hall professional services contract to JLG Architects for a total of $157,425.00

BACKGROUND (Consistency with Adopted Plans and Policies, if applicable)

JLG Architects was selected by RFP to provide design services for the New City Hall project located at 316 N 26th Street.

The Phase I contract for master planning and schematic design services was approved by Council in December 2021 for $195,000.
The contract for Phases II & III for design development, construction drawings, and construction administration was approved by Council in May 2022 for $1,063,050.

Amendments #1 and #2 have also been added to the scope of work:
   - Amendment #1 (5/12/23): $103,970 (Structural Engineering Services ($5,900) and A/V Design ($98,070))
   - Amendment #2 (7/10/23): $53,250 (Electrical Fault Study and Full Building Generator Back-up Design)

Total Design Fees Under Contract before this Amendment: $1,422,570

Additional Design Services that have been added to the scope of work for the design team include: Complete window replacement, an A/V specialist to assist with ensuring well-designed state-of-the-art systems throughout the courtrooms, meeting rooms, EOC, and Council Chambers, along with security system assistance (access control and cameras), and exterior building signage design. 

Amendment #3 includes:
   - Exterior Window Replacement (Design, National Historic Coordination, Bidding, Construction Administration): $110,000
   - Audio/Visual Consultant (Design Drawings, Specifications, Bidding, Construction Administration): $29,800
   - Architectural A/V Coordination: $8,125
   - Building Signage (Design Drawings, Bidding, and Construction Administration): $9,500

Total Design Fees if Amendment #3 is approved: $1,599,995

ALTERNATIVES

City Council may:
  • Approve; or,
  • Not Approve and provide further direction

FISCAL EFFECTS

The New City Hall project is funded from various sources, but primarily the General Fund.

Total design costs to date: $1,422,570
Amendment #3: $157,425
Total design contract if amendment is approved: $1,599,995