Item 1.C.
 
City Council Regular
Date: 04/28/2025
Title: GMP Amendment No. 1A, Amend Park Recreation Campus General Contractor/Construction Manager (GC/CM)
Presented by: Gavin Woltjer
Department: Parks/Rec/Public Lands
Presentation: No
Legal Review: Yes
Project Number: N/A

RECOMMENDATION

Staff recommends that City Council approve the Guaranteed Maximum Price (GMP) Amendment #1A in the amount of $3,226,357.89 for Bid Package #1A with Langlas & Associates, Inc., for the Amend Park Recreation Campus project. This amount is in addition to the previously approved GMP Amendment #1 of $3,894,768.91, resulting in a total GMP of $7,121,126.80.

BACKGROUND (Consistency with Adopted Plans and Policies, if applicable)

The Amend Park Recreation Campus project includes construction of a Courts Facility to serve as a multi-purpose indoor sports complex. The overall scope includes full-sized basketball courts, support facilities, and site infrastructure shared with the Yellowstone Ice Facility.

GMP Amendment #1A includes procurement of the Pre-Engineered Metal Building (PEMB) system and associated erection work to maintain the project schedule. This bid package was publicly advertised, and True North Steel was the apparent low bidder with a base bid of $3,009,215.00 for Bid Package 1A. Associated fees, insurance, bonds, and a 3% contingency bring the GMP Amendment #1A total to $3,226,357.89 (see Exhibit A1A Sumary dated 4/16/2025).

This amendment is consistent with the adopted capital planning and delivery methods established through the City’s agreement with Langlas & Associates, Inc., using a General Contractor/Construction Manager (GC/CM) model under AIA A133–2019.

STAKEHOLDERS

City of Billings – Parks & Recreation,  Administration, and Facilities Division: Project management and oversight
Langlas & Associates, Inc.: General Contractor/Construction Manager (GC/CM)
A&E Design, Inc.: Project architect and lead designer
True North Steel: Selected subcontractor for PEMB procurement and erection
Community Sports Organizations & Public Users: Future users of the Courts Facility
City Council & CIP Oversight: Fiscal approval and policy guidance

ALTERNATIVES

City Council may:
Approve GMP Amendment #1A as presented
Request revisions to scope or cost and defer approval
Reject the amendment, potentially delaying procurement and construction schedule

FISCAL EFFECTS

This GMP Amendment #1A of $3,226,357.89 will be funded using project budget appropriations established in the FY26 Capital Improvement Plan. The overall project remains within the original $20 million budget authorized for the Courts Facility.
This amendment includes no alternates and is based on firm bid values for PEMB scope, consistent with previous contract terms. A 3% contingency is included for Bid Package #1A, and project cost oversight will continue through the City’s Owner’s Representative and City Staff.

SUMMARY

GMP Amendment #1A requests Council approval to authorize $3,226,357.89 for Bid Package #1A related to the procurement and erection of the Pre-Engineered Metal Building (PEMB) for the Amend Park Recreation Campus Courts Facility. This package was bid publicly and awarded to True North Steel as the lowest responsive bidder. Amendment #1A is part of the phased General Contractor/Construction Manager (GC/CM) delivery model with Langlas & Associates and includes construction-related fees, insurance, and contingency. This amendment will maintain project momentum, ensure timely procurement of long-lead items, and keep the overall project within the adopted $20 million budget.