Consent 1.A.1.
Regular City Council Meeting
- Meeting Date:
- 04/09/2012
- TITLE
- W.O. 12-04 Accessibility Ramp Project Bid Award
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
Information
PROBLEM/ISSUE STATEMENT
Bids were received on March 27, 2012, for W.O. 12-04 Accessibility Ramp Project. The project will replace existing and construct new accessibility ramps along portions of Virginia Lane, Lewis Avenue, and 36th Street West. Per the agreement between the U.S. Department of Justice and the City Of Billings, the City is required to construct accessibility ramps on all streets that have been reconstructed or overlaid since 1992.
ALTERNATIVES ANALYZED
The Council may:
• Award the construction contract for W.O. 12-04 Accessibility Ramp Project to J & J Concrete, Inc. in the amount of $249,345.00; or
• Reject all bids and do not award a construction contract for W.O. 12-04. Rejection of bids will delay construction of these improvements until next year.
• Award the construction contract for W.O. 12-04 Accessibility Ramp Project to J & J Concrete, Inc. in the amount of $249,345.00; or
• Reject all bids and do not award a construction contract for W.O. 12-04. Rejection of bids will delay construction of these improvements until next year.
FINANCIAL IMPACT
The City received four (4) bids for this project. The bids were as follows:
| Contractor | Total Construction Bid |
| J & J Concrete | $249,345 |
| CMG Construction | $285,759 |
| Riverside Sand & Gravel | $286,237 |
| H.L. Ostermiller | $299,963 |
The funding for the project was budgeted in FY12 and the source is gas tax. A summary of the funding is as follows:
| Project Budget | $250,000 |
| Previously Encumbered | $0 |
| This Contract | $249,345 |
| Budget Remaining | $655 |
RECOMMENDATION
Staff recommends that Council award the contract for Work Order 12-04 Accessibility Ramp Project to J &J Concrete Inc. in the amount of $249,345.