Consent 1.B.2.
Regular City Council Meeting
- Meeting Date:
- 08/13/2012
- TITLE
- Bid Award for SID 1394 Macona Lane
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
Information
PROBLEM/ISSUE STATEMENT
SID 1394 Macona Lane was created at the July 9, 2012, City Council Meeting. SID 1394 will construct the missing curb and gutter, drive approaches, and street improvements to Macona Lane. Due to the narrow existing right of way, constructing sidewalks is not possible.
The project was bid on July 31, 2012, and three bids were received. CMG Construction, Inc. submitted the lowest responsible bid.
The project was bid on July 31, 2012, and three bids were received. CMG Construction, Inc. submitted the lowest responsible bid.
ALTERNATIVES ANALYZED
The Council may:
- Award SID 1394 construction contract to CMG Construction, Inc. in the amount of $91,325.00; or
- Do not award the contract and reject all bids.
FINANCIAL IMPACT
The following bids were received and evaluated for SID 1394.
The construction will be funded from gas tax, storm funds and Special Improvement District bonds as approved under the Resolution for SID 1394.
| Contractor | Base Bid |
| CMG Construction, Inc. | $91,325.00 |
| Hardrives Construction Inc. | $155,874.13 |
| HL Ostermiller Construction | $177,960.00 |
The construction will be funded from gas tax, storm funds and Special Improvement District bonds as approved under the Resolution for SID 1394.
RECOMMENDATION
Staff recommends that Council award a contract to CMG Construction, Inc. in the amount of $91,325.00.
APPROVED BY CITY ADMINISTRATOR
Attachments
No file(s) attached.