PROBLEM/ISSUE STATEMENT
Bids were received for the W.O. 09-20 Rimrock Road, Forsythia to Shiloh Rd., project on March 26, 2013. The project includes street reconstruction with turn lanes, pavement overlay, curb/gutter, sidewalk, drive approaches, street lighting, traffic signal installation, and water/storm improvements.
ALTERNATIVES ANALYZED
The Council may:
• Award the construction contract for W.O. 09-20 Rimrock Road, Forsythia to Shiloh, to Knife River - Billings in the amount of $3,948,432.50; or
• Reject all bids and do not award a construction contract for W.O. 09-20.
• Award the construction contract for W.O. 09-20 Rimrock Road, Forsythia to Shiloh, to Knife River - Billings in the amount of $3,948,432.50; or
• Reject all bids and do not award a construction contract for W.O. 09-20.
FINANCIAL IMPACT
The City received two (2) bids for this project. The engineer's estimate was $4,426,767.60. The bids were as follows:
| Contractor | Total Construction Bid |
| Knife River - Billings | $3,948,432.50 |
| CMG Construction, Inc. | $4,649,884.00 |
The proposed project will be funded with Property Assessments, Arterial, Water, and Gas Tax funds.
The following is a breakdown of the costs of the $4,689,000 allocated for this project:
| Expense | Amount |
| Previously Encumbered | $331,420.00 |
| Construction (This Contract) | $3,948,432.50 |
| Remaining Funds Available | $133,147.50 |
Remaining funds will be used for construction administration, construction staking, change orders, materials testing, inspection, and other administrative costs.
RECOMMENDATION
Staff recommends that Council award the contract for Work Order 09-20 Rimrock Road, Forsythia to Shiloh, to Knife River - Billings in the amount of $3,948,432.50.