Skip to main content

AgendaQuick™

View Agenda Item

Consent   1.C.
Regular City Council Meeting
Meeting Date:
09/09/2013
TITLE
Compensation Agreement for P-656, Certificate of Survey 3329, Tract 1B (Fed Ex distribution facility property)
PRESENTED BY:
David Mumford
Department:
Public Works
Presentation:

Information

PROBLEM/ISSUE STATEMENT

In order to obtain sanitary sewer service, the developer of the FedEx Ground property, SunCap Property Group, is extending 1,150' of 18" sanitary sewer main in Hesper Road between Gabel Road and Shiloh Road.  The extension was not a planned project in the CIP so the developer will pay the entire cost of the project. The City's Rules and Regulations for Water and Sanitary Sewer include compensation to developers for the entire cost of constructing sanitary sewer mains over 12" in size. As such, the developer desires to be compensated for these costs in full and the Public Works Department proposes that such compensation be accomplished through the attached agreement.  

ALTERNATIVES ANALYZED

The Council may:
  • Accept the compensation agreement; or
  • Do not accept the compensation agreement.  Rejecting the agreement would be contrary to the City's policy which compensates developers who install large diameter public mains as part of their development.

FINANCIAL IMPACT

Based on the lowest bid price for the installation of the sanitary sewer mains, it has been determined that the eligible cost recovery by the developer is $348,722.60. The timing of the City's participation in the project cost is determined in conformance with the budget approved by City Council. 

RECOMMENDATION

Staff recommends that the Council authorize the Mayor to execute the attached compensation agreement. Compensation shall be based on the final sanitary sewer utility costs.

APPROVED BY CITY ADMINISTRATOR

Attachments