Consent 1.A.1.
Regular City Council Meeting
- Meeting Date:
- 06/09/2014
- TITLE
- W.O. 12-43 Back-up Power Phase III
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
PROBLEM/ISSUE STATEMENT
W.O. 12-43 Back-up Power Phase III will provide backup power to the Voelker, Willett, and Leavens Pump Stations in the City's water distribution system. Electrical upgrades to the Chapple Pump Station will also be completed as part of the project. In the event of a power failure at these pump stations, it is critical that they continue to operate so that the distribution system does not have water shortages. The project was advertised on May 8th, 15th, and 22nd in the Billings Times and on the City's Website. Bids were opened on May 27th, 2014, and three bids were received. CEI Electrical Contractors submitted the lowest responsible bid.
ALTERNATIVES ANALYZED
The Council may:
- Award Work Order 12-43; Back-up Power Phase III to CEI Electrical Contractors in the amount of $477,250.00; or
- Do not award Work Order 12-43. If not awarded, the City would need to re-bid or cancel the project, in which case the distribution system may experience water shortages in the event of a power outage.
FINANCIAL IMPACT
The following bids were received and evaluated:
| Contractor | Total Bid |
| CEI Electrical Contractors | $477,250.00 |
| Ace Electric | $510,000.00 |
| Yellowstone Electric | $786,050.00 |
The funding for this project was budgeted in FY14 and the source is Water Funds.
| Budgeted Amount | $840,000 |
| Previously Encumbered | $139,124 |
| This contract | $477,250 |
| Remaining Funds | $223,626 |
RECOMMENDATION
Staff recommends that Council award W.O. 12-43, Back-up Power Phase III, to CEI Electrical Contractors in the amount of $477,250.00.
APPROVED BY CITY ADMINISTRATOR