Consent   1.B.2.
Regular City Council Meeting
Meeting Date:
02/22/2010
TITLE
Bid Award – Replace Existing Primary Digester Boiler System for Wastewater Plant
PRESENTED BY:
David Mumford
Department:
Public Works
Presentation:

PROBLEM/ISSUE STATEMENT

The solids in the primary anaerobic digesters are heated through a heat exchange system with hot water from a 30-year-old boiler system at the Wastewater Plant. To ensure continued, uninterrupted, hot water for the digesters and associated heating for the building, the boiler needs to be replaced.

ALTERNATIVES ANALYZED

The Council may:

1) Approve the bid award; or
2) Not approve the bid award. 

FINANCIAL IMPACT

Bids were publicly advertised for the replacement of the boiler on January 28 and February 4, 2010. Bids were opened on February 9, 2010. The replacement of boiler system is part of the approved CIP and there is adequate funding in the Wastewater Plant budget for this expenditure. The bid results are:
  
Rolin Adkins High-Tec Boilermakers, Inc. $108,830.00
Montana Boiler Service $132,858.00
Star Service $150,500.00
 

RECOMMENDATION

Staff recommends that Council award the bid for the replacement of the primary digester boiler system to Rolin Adkins High-Tec Boilermakers, Inc. in the amount of $108,830.00.

APPROVED BY CITY ADMINISTRATOR