Consent 1.B.
Regular City Council Meeting
- Meeting Date:
- 11/10/2014
- TITLE
- WO 15-08 Exposition Gateway Contract for Professional Services
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
PROBLEM/ISSUE STATEMENT
The purpose of this project is to reconstruct streets near Exposition Drive between 1st Avenue North and 4th Avenue North in accordance with the Billings Exposition Gateway Concept Plan. The streets included in this project are 3rd Avenue North between Exposition Drive and North 11th Street, 2nd Avenue North between North 9th Street and North 11th Street, North 9th Street between 1st Avenue North and 3rd Avenue North, and North 10th Street between 1st Avenue North and 4th Avenue North. The improvements include water, sanitary sewer, storm drain and street improvements. Staff requested the services of an engineering firm to provide design services for the project and Sanderson Stewart was selected through the Request for Proposals (RFP) process. Other firms considered were KLJ and DOWL HKM. The contract amount is $297,178.
ALTERNATIVES ANALYZED
The Council may:
- Award the Contract for Professional Services to Sanderson Stewart; or
- Do not award the contract. If the contract is not awarded, the construction of the improvements will be delayed.
FINANCIAL IMPACT
The cost of design services is $297,178. The cost of the contract will be paid out of the following:
- East Billings TIF Funds $250,000.00
- Water Funds $30,193.92
- Gas Tax $16,984.08
RECOMMENDATION
Staff recommends that Council authorize the Mayor to execute a Contract for Professional Services with Sanderson Stewart for $297,178 for engineering design.