- W.O. 09-13 Staples Redundant Water Main – BBWA Canal Crossing, Contract Award
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
PROBLEM/ISSUE STATEMENT
Council and the Mayor are asked to consider authorizing and executing a construction contract to install a 36-inch diameter steel casing pipe below and across the Billings Bench Water Association (BBWA) Canal near the west end of Parkhill Drive. This casing is being installed before the water is in the ditch and will be used for a future water main construction project.
Because the BBWA plans to begin operating the Canal by April 15, the company requires that the Canal be crossed by April 1; therefore, it is necessary to install the steel casing pipe under the Canal as soon as possible. In addition to evaluating bids on the base work needed to cross the Canal, bid prices have been evaluated for additive alternates that would extend the casing further beyond the Canal and under a large storm drain and sanitary sewer main, add structural backfillband add flowable fill. Each of the additive alternates are being recommended because they result in a better finished product and are within the budget set aside for this portion of the project.
This project will facilitate the future installation of a 24-inch water main through the steel casing during planned subsequent project work that would extend a redundant water main approximately 6,800 feet to Staples Pump Station. The future water main construction project is currently on schedule for a late March bid opening.
Because the BBWA plans to begin operating the Canal by April 15, the company requires that the Canal be crossed by April 1; therefore, it is necessary to install the steel casing pipe under the Canal as soon as possible. In addition to evaluating bids on the base work needed to cross the Canal, bid prices have been evaluated for additive alternates that would extend the casing further beyond the Canal and under a large storm drain and sanitary sewer main, add structural backfillband add flowable fill. Each of the additive alternates are being recommended because they result in a better finished product and are within the budget set aside for this portion of the project.
This project will facilitate the future installation of a 24-inch water main through the steel casing during planned subsequent project work that would extend a redundant water main approximately 6,800 feet to Staples Pump Station. The future water main construction project is currently on schedule for a late March bid opening.
ALTERNATIVES ANALYZED
The Council may:
• Award the construction contract to Four Beers, Inc.; or
• Do not award the construction contract.
• Award the construction contract to Four Beers, Inc.; or
• Do not award the construction contract.
FINANCIAL IMPACT
Bids were opened on February 23, 2010, for W.O. 09-13 Staples Redundant Water Main – BBWA Canal Crossing with the results listed below:
Base Bid
Engineer’s Estimate: $63,561.00
Four Beers, Inc. dba Stillwater Excavating: $58,984.00
Riverside Sand and Gravel, Inc.: $63,034.00
Western Municipal Construction, Inc.: $63,410.00
COP Construction LLC: $69,004.00
Additive No. 1-1
Engineer’s Estimate: $7,260.00
Four Beers, Inc. dba Stillwater Excavating: $9,460.00
Riverside Sand and Gravel, Inc.: $6,710.00
Western Municipal Construction, Inc.: $10,560.00
COP Construction LLC: $15,664.00
Additive No. 1-2
Engineer’s Estimate: $330.00
Four Beers, Inc. dba Stillwater Excavating: $880.00
Riverside Sand and Gravel, Inc.: $660.00
Western Municipal Construction, Inc.: $220.00
COP Construction LLC: $748.00
Alternate Additive No. 1
Engineer’s Estimate: $4,240.00
Four Beers, Inc. dba Stillwater Excavating: $5,830.00
Riverside Sand and Gravel, Inc.: $4,929.00
Western Municipal Construction, Inc.: $4,240.00
COP Construction LLC: $5,989.00
Total Base Bid Plus Additives and Alternate
Engineer’s Estimate: $74,596.00
Four Beers, Inc. dba Stillwater Excavating: $73,670.00
Riverside Sand and Gravel, Inc.: $73,743.00
Western Municipal Construction, Inc.: $77,900.00
COP Construction LLC: $89,603.00
Project funding will be from City water funds.
Base Bid
Engineer’s Estimate: $63,561.00
Four Beers, Inc. dba Stillwater Excavating: $58,984.00
Riverside Sand and Gravel, Inc.: $63,034.00
Western Municipal Construction, Inc.: $63,410.00
COP Construction LLC: $69,004.00
Additive No. 1-1
Engineer’s Estimate: $7,260.00
Four Beers, Inc. dba Stillwater Excavating: $9,460.00
Riverside Sand and Gravel, Inc.: $6,710.00
Western Municipal Construction, Inc.: $10,560.00
COP Construction LLC: $15,664.00
Additive No. 1-2
Engineer’s Estimate: $330.00
Four Beers, Inc. dba Stillwater Excavating: $880.00
Riverside Sand and Gravel, Inc.: $660.00
Western Municipal Construction, Inc.: $220.00
COP Construction LLC: $748.00
Alternate Additive No. 1
Engineer’s Estimate: $4,240.00
Four Beers, Inc. dba Stillwater Excavating: $5,830.00
Riverside Sand and Gravel, Inc.: $4,929.00
Western Municipal Construction, Inc.: $4,240.00
COP Construction LLC: $5,989.00
Total Base Bid Plus Additives and Alternate
Engineer’s Estimate: $74,596.00
Four Beers, Inc. dba Stillwater Excavating: $73,670.00
Riverside Sand and Gravel, Inc.: $73,743.00
Western Municipal Construction, Inc.: $77,900.00
COP Construction LLC: $89,603.00
Project funding will be from City water funds.
RECOMMENDATION
Staff recommends that Council award a construction contract for W.O. 09-13 Staples Redundant Water Main – BBWA Canal Crossing to Four Beers, Inc. in the amount of $73,670.00.
APPROVED BY CITY ADMINISTRATOR
Attachments