Consent 1.A.3.
Regular City Council Meeting
- Meeting Date:
- 04/13/2015
- TITLE
- W.O. 14-09--Briarwood Reservoir Expansion, Contract Award
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
PROBLEM/ISSUE STATEMENT
Zone 4 South of the City's water distribution system serves the Briarwood area. It is greatly deficient in the amount of water storage needed to meet peak usage and fire flow demands. To alleviate this problem, W.O. 14-09 includes the construction of a new 750,000 gallon prestressed concrete water reservoir; all associated piping, valves, and site work; and demolition and removal of the existing 186,000 gallon tank. The project includes provisions for an aeration mixing system in the new reservoir to help reduce issues with water age and disinfection by-products; instrumentation control modifications; and electrical modifications. Due to a very limited area for the tank site, the existing tank will be taken off-line and removed before starting construction of the new tank, and a temporary tank and piping system will be placed into service.
The project was advertised March 12 thru March 26 in the Billings Times and on the City's website. Bids were opened March 31, 2015 and there were two bidders. Western Municipal submitted the apparent low bid. Staff requests that the City Council award a contract based on those bids.
The project was advertised March 12 thru March 26 in the Billings Times and on the City's website. Bids were opened March 31, 2015 and there were two bidders. Western Municipal submitted the apparent low bid. Staff requests that the City Council award a contract based on those bids.
ALTERNATIVES ANALYZED
The Council may:
• Award a construction contract to Western Municipal Construction in the amount of $3,043,112.00; or
• Reject all bids, which will delay the project and the ability to provide needed water storage.
• Award a construction contract to Western Municipal Construction in the amount of $3,043,112.00; or
• Reject all bids, which will delay the project and the ability to provide needed water storage.
FINANCIAL IMPACT
| CONTRACTOR(S) | COP Construction | Western Municipal Construction | |
| TOTAL LUMP SUM BASE BID | $ 3,327,000.00 | $ 3,043,112.00 |
The low bidder is Western Municipal Construction. The project is being funded from a SRF (State Revolving Fund) loan and water funds budgeted in FY 15.
RECOMMENDATION
Staff recommends that Council approve the award of W.O. 14-09--Briarwood Reservior Expansion to Western Municipal Construction in the amount of $3,043,112.00.