Skip to main content

AgendaQuick™

View Agenda Item

Regular   6.
Regular City Council Meeting
Meeting Date:
04/12/2010
TITLE
W.O. 08-21 Lake Elmo Drive - Main St to Wicks Ln - Public Hearing and Resolution Ordering Improvements
PRESENTED BY:
David Mumford
Department:
Public Works
Presentation:

PROBLEM/ISSUE STATEMENT

On March 22, 2010, Council passed a Resolution of Intent for this project and established a Public Hearing date of April 12, 2010. After conducting the Public Hearing, in order to proceed with construction of the project, Council must pass a resolution ordering construction of improvements.

This project was developed to improve the street and provide a pedestrian facility on Lake Elmo Drive from Main Street to Wicks Lane. The project will include street reconstruction with turn lanes, pavement overlay, curb, gutter, sidewalk, approaches, storm drain improvements, and asphalt multi-use trail.

ALTERNATIVES ANALYZED

The Council may:
• Pass a resolution ordering construction of the improvements; or
• Do not pass a resolution ordering construction of the improvements.

FINANCIAL IMPACT

The proposed project is funded through multiple sources, including direct property assessments for a total estimated project cost of $2,744,903 as follows:

Estimated Assessed Costs $472,000
CTEP $552,591 
Storm Drain Funds $510,000
Gas Tax Funds $1,655,000

Funding for the proposed project is included in the Fiscal Year 2010 budget.

RECOMMENDATION

Staff recommends that Council pass a resolution ordering construction of the improvements identified in Work Order 08-21, Lake Elmo Drive - Main St to Wicks Ln.

APPROVED BY CITY ADMINISTRATOR

Attachments