Consent 1.A.5.
Regular City Council Meeting
- Meeting Date:
- 04/25/2016
- TITLE
- W.O. 16-01 Schedule 2A, Sanitary Sewer Replacement
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
PROBLEM/ISSUE STATEMENT
W.O. 16-01, Schedule 2A, Sanitary Sewer Replacement will consist of replacing 531 feet of 36-inch sanitary sewer main and construction of 6 new specialty lined manholes at the Waste Water Treatment Plant. All the raw sewage from the Billings Heights flows into this section of influent piping. The existing piping and manholes are corroded and need replacement. Although this project is at the Waste Water Treatment Plant (WWTP), the piping is part of the collection system and is being replaced with the annual replacement projects instead of when the WWTP is reconstructed later in FY 16 and FY 17.
The project was advertised on March 24th, 31st, and April 7th in the Billings Times and on the City's Website. Bids were opened on April 12, 2016, and five bids were received. COP Construction, LLC submitted the lowest responsible bid.
The project was advertised on March 24th, 31st, and April 7th in the Billings Times and on the City's Website. Bids were opened on April 12, 2016, and five bids were received. COP Construction, LLC submitted the lowest responsible bid.
ALTERNATIVES ANALYZED
City Council may:
- Approve the construction contract for WO 16-01 with COP Construction, LLC in the amount of $555,221.00; or,
- Do not approve the construction contract. If the project is not approved, the sewer system will continue to corrode and could fail, causing sanitary sewer overflows for which the City could be fined.
FINANCIAL IMPACT
The following bids were received and evaluated:
Funding for this project will be from Wastewater Funds.
| Contractor | Bid Amount |
| Dick Anderson | $797,500.00 |
| Western Municipal Construction, Inc. | $753,240.00 |
| Williams Civil Construction | $587,523.00 |
| COP Construction, LLC | $555,221.00 |
| Wilson Bros. Construction | $688,485.00 |
Funding for this project will be from Wastewater Funds.
| Budget | $3,800,000.00 |
| Previously Encumbered | $734,127.00 |
| This Contract | $555,221.00 |
| W.O. 16-01 Sch 4 Southside Sewer (also awarded this Council Meeting) | $420,953.00 |
| Remaining Budget | $2,089,699 |
RECOMMENDATION
Staff recommends that Council approve a contract with COP Construction, LLC for W.O. 16-01, Schedule 2A Sanitary Sewer Replacement in the amount of $555,221.00.