- TITLE
- Billings Police Department Firearms Range Building - Contract with Cucancic Construction, Inc.
- PRESENTED BY:
- Rich St. John
- Department:
- Police
Presentation:
PROBLEM/ISSUE STATEMENT
The Billings Police Department Firearms Range is located at 2327 Hillcrest Road and the department wishes to construct a building for shelter and storage purposes. The Invitation for Bids (IFB) seeking responses from qualified contractors to construct a firearms range building was advertised on May 5 and 12, 2016. Five contractor's responded to the IFB, and are as follows:
- Hardy Construction - $170,000
- General Contractors - $137,383
- DPS Company - $113,950
- Heart Mountain Construction - $109,140
- Cucancic Construction - $108,164
ALTERNATIVES ANALYZED
City Council may:
- Approve the contract with Cucancic Construction, Inc. or;
- Disapprove the contract with Cucancic Construction, Inc. and provide guidance to staff on the Council's preferred alternative.
FINANCIAL IMPACT
This project will be funded through a previously approved donation of $50,000 from Phillips 66, and the remaining funds have been budgeted for in the Police Department fund.
RECOMMENDATION
Staff recommends that the City Council approve the contract for $108,164 with Cucancic Construction, Inc. to construct a firearms range building.