Consent   1.A.1.
Regular City Council Meeting
Meeting Date:
09/12/2016
TITLE
Roof Replacement of Fire Station #5
PRESENTED BY:
Bruce McCandless
Department:
City Hall Administration
Presentation:

PROBLEM/ISSUE STATEMENT

The roof at Fire Station #5 was assessed by CTA Envelope Specialists and is in need of replacement.  The replacement is planned and budgeted in the FY17 Budget.  Bids will be opened on September 6, after the Council agenda is published.  Since the remaining construction season is so short, staff will provide additional information about bidders and will recommend an award to Council by Friday, September 9.

ALTERNATIVES ANALYZED

CTA evaluated the roof options and are recommending replacement with a 60 mil EPDM Roof.  An Invitation for Bid was advertised on August 25 and September 1st. Bids were opened on September 6, 2016 and we received four (4) qualified bids.

The low bid was Perfect 10 Roofing for $46,995.00. The other bids were from Metal Works MT, Summit Roofing, and Commercial Roofing. Their bids were $121,352.00, $62,125.00, and $68,300.00, respectively.

Council may:
  • Approve the low bid and award a contract, or;
  • Reject all bids and provide staff with additional guidance.

FINANCIAL IMPACT

The FY 17 budget for this roof replacement is $72,100, so project is within budget.

RECOMMENDATION

Staff recommends awarding the contract for replacing the Fire Station #5 roof to Perfect 10 Roofing for $46,995.00. Staff also recommends approval as we are hoping to complete this project by late Fall. 

APPROVED BY CITY ADMINISTRATOR