Consent 1.C.
Regular City Council Meeting
- Meeting Date:
- 05/10/2010
- TITLE
- WO 09-03 2009 Street Maintenance City Crack Seal Change Order #3 (Final)
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
PROBLEM/ISSUE STATEMENT
The City Crack Seal project is part of the ongoing Street Preventative Maintenance Program supported by the City Council since 1985. The crack seal contract provides crack sealing of approximately 15 miles of various streets throughout the city before they are chip sealed. The contract was awarded to Z & Z Seal Coating in the amount of $86,084.38. The original contract included approximately 51,750 lbs of crack filler. Change Order #1 was approved by the City Administrator on October 26, 2009, for an additional 5,600 lbs of crack filler at a cost of $8,600. It becomes necessary to add approximately 18,000 lbs of additional crack filler to finish the project. Crack seal project quantities are based on typical sections of the project. In a couple of areas in the Heights, significantly more crack filler was needed because there were many more cracks than a typical street in the project area. The cost to add 18,000 lbs of crack filler was $27,540.00. City Council approved Change Order #2 in the amount of $27,540.00 on December 14, 2009. Unfortunately, this winter created more cracks in the Heights than what was anticipated, and it took approximately 2700 lbs of crack filler beyond what was approved to finish the project. Change Order #3 reconcilies the final quantities with the quantities approved with the contract. Change Order #3 is the final change order and results in a net increase of $4,137.12.
ALTERNATIVES ANALYZED
The Council may:
• Approve Change Order #3 (Final) to WO 09-03, City Crack Seal in the amount of $4,137.12; or
• Do not approve Change Order #3 (Final) to WO 09-03, City Crack Seal.
• Approve Change Order #3 (Final) to WO 09-03, City Crack Seal in the amount of $4,137.12; or
• Do not approve Change Order #3 (Final) to WO 09-03, City Crack Seal.
FINANCIAL IMPACT
Funding for WO 09-03, 2009 Street Maintenance City Crack Seal, will be provided from Gas Tax Funds. The original contract was for $86,084.38. With the approval of Change Order #1, Change order #2, and change order #3, the new contract amount will be $126,361.50. The original engineer's estimate was $118,675.00. There is $600,000 budgeted in FY '10 for PAVER. After the crack seal, the remaining funds will be utilized for the City Chip Seal which was awarded in the amount of 420,810.22 at the February 8, 2010, City Council Meeting.
| CIP Project #ENG98 | |
| CIP Budgeted Amount | $600,000.00 |
| Previous Encumbrances City Chip Seal Awarded 2/8/10 | $420,810.22 |
| Budget Fund Balance (after this change order) |
$52,828.28 |
RECOMMENDATION
Staff recommends that Council approve Change Order #3 (Final) for the 2009 Street Maintenance City Crack Seal Project with Z & Z Seal Coating in the amount of $4,137.12.