TITLE
W.O. 08-21 Lake Elmo Drive - Main St to Wicks Ln Bid Award
PRESENTED BY:
David Mumford
Department:
Public Works
Presentation:

PROBLEM/ISSUE STATEMENT

Bids were received for W.O. 08-21 Lake Elmo Drive on April 27, 2010. The project will include street reconstruction with turn lanes, pavement overlay, curb, gutter, sidewalk, drive approaches, storm drain improvements, and an asphalt multi-use trail along Lake Elmo Drive from Main Street to Wicks Lane.

ALTERNATIVES ANALYZED

The Council may:
• Award the contract W.O. 08-21 to Riverside Sand & Gravel in the amount of $1,689,497.00; or
• Reject all bids and do not award contract for W.O. 08-21

FINANCIAL IMPACT

We received five (5) bids for this project as follows:

Engineer's Estimate $2,252,130.00

Contractor Total Construction Bid
Riverside Sand & Gravel $1,689,497.00
H.L. Ostermiller $1,801,380.30
Knife River $1,932,237.50
CMG Construction, Inc. $2,025,653.00
JEM $2,299,609.10












The following is a breakdown of the project funding sources available:

Estimated Assessed Costs $472,000
CTEP $552,591
Storm Drain Funds $510,000
Gas Tax Funds $1,655,000                             
Total Funding Available $3,189,591.00

The following is a breakdown of the costs of the $3,189,591.00 allocated for this project:

Design $233,113.00 (PE contract)
Staking $126,590.00
Construction $1,689,497.00                                  
Remaining Funds $1,140,391.00

Remaining funds will be used for change orders, materials testing, inspection, and other administrative costs.

RECOMMENDATION

Staff recommends that Council award the bid for Work Order 08-21 Lake Elmo Drive, Main Street to Wicks Lane, to Riverside Sand & Gravel in the amount of $1,689,497.00.