TITLE
Bid Award: W.O. 19-03 Contract No. 3 City Crack Seal/Mastic
PRESENTED BY:
David Mumford
Department:
Public Works
Presentation:
No

PROBLEM/ISSUE STATEMENT

W.O. 19-03, Contract No. 3 City Crack Seal/Mastic is part of the 2019 Street Maintenance program.  Bids were opened on February 26th. There were two bids received and Wharton Asphalt, LLC submitted the lowest responsible bid. Annually, staff identifies streets proposed for preventative maintenance. Staff typically bids this work in three contracts: chip seal resurfacing, overlay resurfacing, and crack sealing. This contract will provide crack sealing and mastic filling on approximately 17 miles of City streets. The project was advertised on February 8, 15, and 22 in the Yellowstone County News and on the City's website.

ALTERNATIVES ANALYZED

The Council may:
  • Award W.O. 19-03, Contract No. 3 City Crack Seal/Mastic, to Wharton Asphalt, LLC, in the amount of $336,624.25; or
  • Do not award a contract and reject all bids.  If this project is not awarded, the deferred maintenance of City streets will increase.

FINANCIAL IMPACT

The following bids were received and evaluated:
Contractor Base Bid
Wharton Asphalt, LLC $336,624.25
Z&Z Seal Coating, Inc. $412,437.80

The funding for the project was budgeted in FY19 and the source is gas tax.
Project Budget $2,875,000.00
Previously Encumbered $0
W.O. 19-03 Contract No. 1 City Overlay $1,297,604.70
W.O. 19-03 Contract No. 2 City Digouts $925,429.45
This Contract $336,624.25
Budget Remaining $315,341.60

RECOMMENDATION

Staff recommends the City Council award a contract for W.O. 19-03, Contract No. 3 City Crack Seal/Mastic, to Wharton Asphalt, LLC, in the amount of $336,624.25.

APPROVED BY CITY ADMINISTRATOR