Regular City Council Meeting
- Meeting Date:
- 02/24/2020
- TITLE
- Centennial Park Development - Change Order No. 3, FirstMark Construction
- PRESENTED BY:
- Mike Whitaker
- Department:
- Parks/Rec/Public Lands
Presentation:
No
PROBLEM/ISSUE STATEMENT
On June 25, 2018, as part of the FY2019 Budget, Council approved funding in the amount of $2,460,000.00 to develop the first phase of Centennial Park. As part of the budgeting process for FY2020, Council approved $176,204.00 to fund the completion of the parking lot at Centennial Park. This amount was paid for with PD1 funds as a part of the FY2020 budget process. Also, the Friends of Billings Dog Parks donated $80,000.00 to aid in the development of the dog off leash area at the park. The total budget for the first phase of development of Centennial Park grew to $2,716,204.
Change Order No. 3, to FirstMark Construction, in the amount of $4,543.90, accounts for minor additions to pay for items that were unexpected as part of the construction operation. Also it contains deductions taken out of the project that were not essential in the first phase of construction and would be in the way or damaged as part of future phases of construction. See Change Order No. 3, Attachment A. Change Order #3 is coming before Council for consideration and approval because it exceeds the signing authority of the City Administrator for this project. If Change Order No. 3 is approved, the remaining project budget will be $23,107.
| General Fund | Cash-in-Lieu | Park District 1 | Donations | Total | |
| Steiner Thuesen Consulting Fee | 278,614 | 64,085 | 342,699 | ||
| City Building Department Review Fee | 1,058 | 243 | 1,301 | ||
| Construction - FirstMark General Contractor | 1,581,712 | 363,813 | 1,945,525 | ||
| Change Order #1 (Pave Parking Lot) | 176,204 | 176,204 | |||
| Change Order #2 (Dog Park Fencing, Drinking Fountains) | 2,087 | 480 | 80,000 | 82,567 | |
| Utility Fee | 4,472 | 1,029 | 5,500 | ||
| Public Works System Development Fee | 45,577 | 10,483 | 56,060 | ||
| Pre-manufactured Restroom | 63,981 | 14,716 | 78,697 | ||
| Change Order #3 (Pending Approval) | 3,694 | 850 | - | - | 4,544 |
| TOTAL | 1,981,194 | 455,699 | 176,204 | 80,000 | $ 2,693,097 |
| Budget Amount | 2,000,000 | 460,000 | 176,204 | 80,000 | 2,716,204 |
| Budget Remaining | 18,806 | 4,301 | 0 | 0 | 23,107 |
Change Order No. 3, to FirstMark Construction, in the amount of $4,543.90, accounts for minor additions to pay for items that were unexpected as part of the construction operation. Also it contains deductions taken out of the project that were not essential in the first phase of construction and would be in the way or damaged as part of future phases of construction. See Change Order No. 3, Attachment A. Change Order #3 is coming before Council for consideration and approval because it exceeds the signing authority of the City Administrator for this project. If Change Order No. 3 is approved, the remaining project budget will be $23,107.
ALTERNATIVES ANALYZED
City Council may:
- Approve Change Order No. 3, to FirstMark Construction, for the amount of $4,543.90, or;
- Disapprove Change Order No. 3 and provide staff with additional guidance.
FINANCIAL IMPACT
Sufficient budget authority exists to cover the cost of this change order, approval will not require additional budget authority. If the Change order #3 is approved, the remaining project budget will be $23,000.
RECOMMENDATION
Staff recommends that Council approve Change Order No. 3, to FirstMark Construction, in the amount of $4,543.90.