PROBLEM/ISSUE STATEMENT
Bids were received and evaluated for WO 09-14, Wicks and Saint Andrews Signal, on September 14, 2010. This project will construct a traffic signal at the intersection of Wicks Lane and Saint Andrews Drive. In addition, the project will construct ADA ramps at this intersection.
ALTERNATIVES ANALYZED
The Council may:
- Award the contract for Work Order 09-14 to Ace Electric in the amount of $107,918; or
- Do not award a contract for Work Order 09-14, reject all bids and advise staff on next steps.
FINANCIAL IMPACT
Funding for WO 09-14 Wicks and Saint Andrews Signal will be provided from Arterial Funds. The City received three bids for this project as follows:
| Contractor | Total |
| Engineer's Estimate | $125,959.90 |
| Ace Electric | $107,918.00 |
| Yellowstone Electric | $112,658.55 |
| Midland Electric | $121,500.00 |
RECOMMENDATION
Staff recommends that Council approve the construction contract for WO 09-14 Wicks and Saint Andrews Signal with Ace Electric in the amount of $107,918.