Item 1.A.2.
 
City Council Regular
Date: 05/10/2021
Title: Community Center Hail Repair
Presented by: John Caterino, Facilities Supervisor
Department: City Hall Administration
Presentation: No

RECOMMENDATION

Staff recommends that City Council reject all bids for the Billings Community Center Hail Repair project.

BACKGROUND (Consistency with Adopted Plans and Policies, if applicable)

The Billings Community Center, located at 390 N 23rd St., sustained significant hail-related damage in August 2019. This project includes the removal and replacement of the existing roofing and siding systems. 

The project was advertised on 04/02/2021 and 04/09/2021 in Yellowstone County News and on the City's website. 

Bids were opened on 04/27/2021, and 1 non-responsive bid was received. The bidder failed to submit a Bid Bond. 
 

ALTERNATIVES

There are no viable alternatives to rejecting the bid.

FISCAL EFFECTS

None - bid was non-responsive.