Staff proposes the Planning Board recommend conditional approval of the preliminary plat of High Sierra Subdivision, 20th Filing to the City Council, and adopt the Findings of Fact as presented in the staff report.
BACKGROUND (Consistency with Adopted Plans and Policies, if applicable)
On August 2, 2021, Sanderson Stewart, agent for High Sierra II, Inc., applied for preliminary major plat approval for High Sierra Subdivision, 19th Filing. The proposed subdivision creates 17 lots for residential development. The subject property is generally located west of Entrada Road and east of Matador Avenue in Billings Heights. The property is zoned Suburban Neighborhood (N3). The proposed lots will follow the current zoning for lot frontage.
VARIANCES REQUESTED
The applicant is not requesting a variance from the subdivision regulations.
PROPOSED CONDITIONS OF APPROVAL
Pursuant to Section 76-3-608(4), MCA, the following conditions are recommended to reasonably minimize potential adverse impacts identified within the Findings of Fact.
VARIANCES REQUESTED
The applicant is not requesting a variance from the subdivision regulations.
PROPOSED CONDITIONS OF APPROVAL
Pursuant to Section 76-3-608(4), MCA, the following conditions are recommended to reasonably minimize potential adverse impacts identified within the Findings of Fact.
- To minimize the effects on local service, prior to final plat approval, the applicant will coordinate with the USPS for locating and providing the correct amount of space for safely delivering the mail to the residents.
- Minor changes may be made in the SIA and final documents, as requested by the Planning, Legal or Public Works Departments to clarify the documents and bring them into the standard acceptable format.
- The final plat shall comply with all requirements of the City of Billings Subdivision Regulations, rules, regulations, policies, and resolutions of the City of Billings, and the laws and Administrative Rules of the State of Montana.
- Pre-application meeting May 27, 2021
- Preliminary plat application submitted to Planning Division on August 2, 2021
- Departmental review meeting August 19, 2021
- Preliminary plat resubmittal August 26, 2021
- Planning Board plat review September 14, 2021
- Planning Board public hearing September 28, 2021
- Preliminary plat to City Council October 25, 2021
- 60 working-day preliminary plat review period ends October 26, 2021
PLAT INFORMATION
General location: North of Ortega Street and west of Matador Avenue
Legal Description: Lot 5, Block 31, of High Sierra Subdivision 19th Filing
Owner/Subdivider: High Sierra II, Inc.
Engineer and Surveyor: Sanderson Stewart
Existing Zoning: N3
Existing land use: Vacant Lane
Proposed land use: Residential
Gross and Net area: 61.825 acres / 58.245 acres
Proposed number of lots: 63
Lot size: Max: 45.69 acres
Min.: 6,001 square feet
Parkland requirements: Parkland dedication requirement is 1.382 acres. This requirement will be met with a cash in lieu contribution.
General location: North of Ortega Street and west of Matador Avenue
Owner/Subdivider: High Sierra II, Inc.
Engineer and Surveyor: Sanderson Stewart
Existing Zoning: N3
Existing land use: Vacant Lane
Proposed land use: Residential
Gross and Net area: 61.825 acres / 58.245 acres
Proposed number of lots: 63
Lot size: Max: 45.69 acres
Min.: 6,001 square feet
Parkland requirements: Parkland dedication requirement is 1.382 acres. This requirement will be met with a cash in lieu contribution.
STAKEHOLDERS
There are no stakeholder responses at this time. Stakeholder input will be received at a public hearing scheduled for this subdivision on September 28, 2021.
ALTERNATIVES
In accordance with state law, the City Council has 60 working days to act upon this major preliminary plat. The 60 working day review period for the proposed plat ends on October 26, 2021. State and City subdivision regulations also require that preliminary plats be reviewed using specific criteria, as stated within this report. The City may not unreasonably restrict an owner's ability to develop land if the subdivider provides evidence that any identified adverse effects can be mitigated. Within the 60 working day review period, the City Council is required to:
1. Approve;
2. Conditionally Approve; or
3. Deny the Preliminary Plat
1. Approve;
2. Conditionally Approve; or
3. Deny the Preliminary Plat
FISCAL EFFECTS
This plat will have no fiscal impacts on the City/County Planning Division.
SUMMARY
One of the purposes of the City’s subdivision review process is to identify potential negative effects of property being subdivided. Negative effects that are identified become the subdivider’s responsibility to mitigate. Various City departments, private service/utility providers and the affected school district/s, have reviewed this application and provided input on effects and mitigation. The Findings of Fact, which are presented as an attachment, discuss potential negative impacts of the subdivision and conditions of approval are recommended as measures to further mitigate any impacts. In this case, there were found to be minimal impacts from this proposed subdivision.